Rehabilitating a thermal energy storage system through commissioning Conference Paper uri icon

abstract

  • A thermal energy storage system was installed in a 37,000 ft2 hospital in April 1992. The chiller had to be operated every summer during peak demand periods until the authors rehabilitated system through building commissioning in late 1995. This paper presents information about the building systems, commissioning activities, and the measured energy savings.

published proceedings

  • ASHRAE Transactions

author list (cited authors)

  • Liu, M., Veteto, B., & Claridge, D. E.

complete list of authors

  • Liu, M||Veteto, B||Claridge, DE

publication date

  • December 1999