State of production plan reliability- A case study from India Conference Paper uri icon

abstract

  • In the quest to assess the state of production plan reliability on a mid-sized residential project in India, a case study is conducted with production planning inspired by Last Planner System of production control (LPS). The residential construction sector in India is expected to grow at more than 26% per annum till 2014. However, India does not compare favorably with other countries in the efficient execution of projects and the government has pointed out the need to enhance productivity to meet the increasing rate of economic growth with the best use of labor and resources. Variability and uncertainty in construction project production is identified as an area of improvement. In order to investigate the current state of production plan reliability on mid-sized residential construction projects, a case study is conducted on a 17-story residential project in Mumbai, India. The results indicate that initially, production plans prepared by the project team were highly unreliable with a high degree of variability, but they improved toward the end of the project. Production plan reliability measured as Percentage Plan Complete, also known as Percent Promises Complete, (PPC) varied from 25% to 100% over a period of 24 weeks. The major reasons for production plan failure were bad weather, labor unavailability, material unavailability, untimely drawings and decisions, city regulations, government compliance and unplanned holidays. A feedback loop was put in place and project participants were interviewed at the end of the project. They reported improvement in production plan reliability and indirect cost and quality benefits. This case study provides a hint to the state of production plan reliability in Indian residential construction projects. However, additional and cross sectional research on a variety of residential projects is needed to statistically validate the findings and understand the current state of production plan reliability in India.

published proceedings

  • IGLC 2012 - 20th Conference of the International Group for Lean Construction

author list (cited authors)

  • Porwal, V., Dave, B., Fernandez-Solis, J., Koskela, L. J., & Mehta, H. S.

complete list of authors

  • Porwal, V||Dave, B||Fernandez-Solis, J||Koskela, LJ||Mehta, HS

publication date

  • December 2012